UCI PMC 2014-2015 Project Plan

UCI PMC 2014-2015 Project Plan

The following is a work-in progress project plan for the UCI PMC for the 2014-2015 year

2014-2015 Objectives

  • Design, implement, test and use a project approval process/workflow in ServiceNow that can be used for any type of OIT project
  • Collect, refine and communicate PM tools, resources and best practices
  • Provide consultative PM support for any identified OIT projects

Workstream Activities

  • Project Approval Framework and ServiceNow Workflow
    • Review current OIT project approval processes being used my larger groups (Eric P)
    • Design approval process and framework that can apply across OIT groups (All)
    • Discuss ServiceNow implementations with other UC campuses
    • Train PMC members on ServiceNow PM and workflow basics
    • Define the OIT Project Approval Process workflow in ServiceNow
      • Maybe start after Thanksgiving 2014
    • Exercise the process and ServiceNow workflow with a small project
    • Refine the ServiceNow workflow as needed
    • Develop and execute a communications plan for OIT groups to begin using the process and ServiceNow workflow
  • Collect, Refine and Communicate PM Tools, Resources and best practices
    • Review Eric P's survey results to ID any existing tools and best practices to promote
    • Inventory existing tools and resources
      • Review, discuss relevance
    • Identify tool/resource gaps re: PM best practices
      • Identify pain points - things we commonly struggle with where a template or something else could help
        • Estimation model, Brown-bag lunch talks, etc.
        • Consider "lessons learned" from some of our past projects
    • Build out the PMC Tools and Resources wiki pages
    • Develop additional required tools/resources and link to the PMC Tools and Resources wiki pages
    • Develop and execute a communications plan for informing the broader OIT community about these resources
  • PM Consultation for Identified OIT Projects
    • Identify projects in need of PM consultation support, including the project lead and stakeholders (Kian)
      • PMC members ID or OIT Sr Mgrs ID
    • Meet with project lead to explore what consultative support would be helpful
    • Connect available PMC members as peer-support to those project leads
    • Track any essential support activities for later evaluation by the PMC to determine if/how this model could continue/improve
    • End-of-year review of any PM consultative support activities and make PMC recommendations for 2015-2016

General

  • PMC members work on related activities in addition to their primary work
  • Use the wiki and email for effective communication
  • Monthly meetings for collaboration and as checkpoints for ensuring progress on activities

Schedule/Plan

 

Workstream: Project Approval Framework

 

Item #

 

Activity

 

Assignee

Target/Actual

Start Date

Target/Actual

End Date

 

Notes

1Review current OIT project approval processes bei9ng used by larger groupsEric P 9-19-2014

OIT SDLC is primary process

Most OIT Teams support business units get local business unit management approval, but it's less formal in many cases

2Design approval process and framework that can apply across all OIT GroupsEric T (All) 1-26-2015

OIT Project Approval Framework

3Discuss Service Now implementations with other UC campuses re: PM processesEric P 11-14-2015No other UC campuses are using SN for PM to any significant degree
4Train PMC members learn ServiceNow PM and workflow basicsAll 1-26-2015

Demonstrated at various PMC meetings

5Define the OIT Project Approval Process workflow in ServiceNowEric P11-15-20155-15-2015?5-15-2015: Eric P finished config of latest version for pilot testing in production
6Exercise the process and ServiceNow workflow with a small projectEric P and Eric T 5-15-2015

4-20 thru 5-12 Eric P and Eric T continued testing/exercises in dev and production connecting UCI PM info to SN Proposal record and recording approvals as reflected in the record's action log.

4-12-2015 Eric P and Eric T did an initial exercise, but found the SN Approval record doesn't work as desired for ongoing approvals, tracking and reporting.  Switching to storing data with the SN Project record.

7Refine the SN WorkflowEric P3-4-20155-15-2015

5-15-2015 Eric P/T testing in production

3-4-205 Eric P's switching from tying OIT Project Proposal template data elements from SN Approval records to the SN Project records - also revising the Project Intake form accordingly

9Final test of workflow with example projects and a couple real projectsEric T5-15-2015 5-15-2015 Eric T entered test projects in project and will ad real projects next
10All PMC members submit select real projects (currently in progress) through the submission and review process to retroactively record approvals and see how data looks in SNEric T (All)  3-4-2015 Waiting for new SN Proposal attributes and revised workflow
11Consider adding all active OIT projects into SN so it represents a fairly complete picture of activityEric T (others)   
12Develop and execute a communications plan for OIT groups to begin using the process and ServiceNow workflow    
      

 

 

Workstream: Tools and Resources

 

Item #

 

Activity

Target/Actual

Start Date

Target/Actual

End Date

 

Notes

1    
1.1    
1.2    
2    
2.1    
3    
3.1    

 

 

Workstream: OIT Project Consultative Support

 

Item #

 

Activity

Target/Actual

Start Date

Target/Actual

End Date

 

Notes

1    
1.1    
1.2    
2    
2.1    
3    
3.1