9/1/2017 – 09/29/2017

Completed

  • Issue on ODI Application resolved.
  • Summer ETL Access established.
  • Grad Aid Staging development put on hold as the source data development is in progress.
  • Grad Aid Change to column names completed.
  • Automation of the ETL process for Legacy data the ones which are complete.

In Progress

  • Testing of ETL connectivity for summer Database.
  • Extension on a table (SZRADAP)from Base line into ODS.
  • Student Mapping.
  • Time to degree report.

Planned

  • Continue to work with the remaining technical leads to identify the legacy data connectivity.
  • Start the ETL Development of the known Legacy inputs.

 

6/16/2017 – 08/31/2017

Completed

...