ARRA Report Period Schedule

 

12/31/2013 Period

 

 

Date

Note/Comment

Report Begin

12/28/2013

 

Financial Data

01/09/2014

The 5th working day of the month.

Department Entry Cutoff

01/10/2014

Last day department can enter values.

Email Reminder

---

No reminder email this reporting period.

Warning Buffer

01/09/2014 (+0)

Entered as number of days after Financial Month End Date.

Warning buffer typically starts the day before Department Entry Cutoff.

Test Upload   ---Performed to validate bad / missing data prior to first upload
First Upload  ---No first upload this quarter
Report Modifications---
No Report Modifications period this quarter
Final Upload 01/10/2014
 


09/30/2013 Period

 

Date

Note/Comment

Report Begin

09/28/2013

 

Financial Data

10/07/2013

The 5th working day of the month.

Department Entry Cutoff

10/10/2013

Last day department can enter values.

Email Reminder

---

No reminder email this reporting period.

Warning Buffer

10/09/2013 (+2)

Entered as number of days after Financial Month End Date.

Warning buffer typically starts the day before Department Entry Cutoff.

Test Upload   ---Performed to validate bad / missing data prior to first upload
First Upload  10/07/2013
Report Modifications10/07/2013 - 10/10/2013
 
Final Upload 10/10/2013
May change depending on Evelyn's schedule.

06/30/2013 Period

 

Date

Note/Comment

Report Begin

06/28/2013

 

Financial Data

07/12/2013

Delayed to 12th due to fiscal year end

Department Entry Cutoff

07/15/2013

Last day department can enter values

Email Reminder

---

No reminder email this reporting period

Warning Buffer

07/12/2013 (+3)

Entered as number of days after Financial Month End Date

Test Upload   ---Performed to validate bad / missing data prior to first upload
First Upload  07/05/2013
Report Modifications07/06/2013 - 07/15/2013
 
Final Upload 07/17/2013
Most likely will be on the 17th due to Ryan being on vacation. May change later.

03/31/2013 Period

 

Date

Note/Comment

Report Begin

03/28/2013

 

Financial Data

04/05/2013

Approximately the 5th working day of the month 

Department Entry Cutoff

04/10/2013

Last day department can enter values

Email Reminder

---

No reminder email this reporting period

Warning Buffer

04/08/2013  (+2)

Entered as number of days after Final Upload / Financial Month End Date

Test Upload   ---Performed to validate bad / missing data prior to first upload
First Upload  04/05/2013
Report Modifications04/06/2013 - 04/10/2013
 
Final Upload 04/10/2013
 

12/31/2012 Period

 

Date

Note/Comment

Report Begin

12/20/2012

 

Financial Data

01/08/2013 

Approximately the 5th working day of the month 

Department Entry Cutoff

01/09/2013

Last day department can enter values

Email Reminder

01/02/2013 (+13)

Entered as number of days since Report Begin

Warning Buffer

01/08/2013  (+2)

Entered as number of days from Final Upload / Financial Month End Date

Test Upload   01/10/2013Performed to validate bad / missing data prior to first upload
First Upload  ---No first upload this quarter.
Report Modifications---
No Report correction period this quarter.
Final Upload 01/10/2013This is the only and final upload.

09/30/2012 Period

 

Date

Note/Comment

Report Begin

 09/23/2012

 

Financial Data

10/05/2012  

Approximately the 5th working day of the month 

Department Entry Cutoff

10/09/2012

Last day department can enter values

Email Reminder

NULL (Not sent)

Entered as number of days since Report Begin

Warning Buffer

10/08/2012  (+2)

Entered as number of days from Final Upload / Financial Month End Date

Test Upload   06/05/2012 Performed to validate bad / missing data prior to first upload
First Upload  10/05/2012 This is needed even if estimated due to deadline mandates
Report Modifications10/05/2012 - 10/09/2012If correction period is applicable (typically is)
Final Upload 10/10/2012This is a second upload for adjustments after corrections

06/30/2012 Period

 

Date

Note/Comment

Report Begin

 06/28/2012

When WRT is open for early entry before the break

Financial Data

07/10/2012  

Approximately the 5th working day of the month 

Department Entry Cutoff

07/12/2012

Last day department can enter values

Email Reminder

NULL (Not sent)

Entered as number of days since Begin

Warning Buffer

07/11/2012  (+1)

Entered as number of days since Financial Data

Test Upload   06/05/2012 Performed to validate bad / missing data prior to first upload
First Upload  07/06/2012 This is needed even if estimated due to deadline mandates
Report Modifications07/08/2012 - 07/12/2012If correction period is applicable (typically is)
Final Upload 07/13/2012This is a second upload for adjustments after corrections

03/31/2012 Period 

 

Date

Note/Comment

Report Begin

03/28/2012

When WRT is open for early entry before the break

Financial Data

04/05/2012 

Approximately the 5th working day of the month 

Department Entry Cutoff

04/12/2012 

Last day department can enter values

Email Reminder

NULL  

Entered as number of days since Begin

Warning Buffer

01/11/2012 (+6)

Entered as number of days since Financial Data

Test Upload (Test)  03/05/2012 Performed to validate bad / missing data prior to first upload
Report Modifications03/08/2012 - 01/12/2012If correction period (CP) applies.
Report Upload (Real) 03/06/2012, 03/13/2012*First, *Second is for upload of CP applies

12/31/2011 Period 

 

Date

Note/Comment

Report Begin

12/28/2011

When WRT is open for early entry before the break

Financial Data

01/09/2012 

Approximately the 5th working day of the month 

Department Entry Cutoff

01/12/2012 

Last day department can enter values

Email Reminder

01/04/2012 -> 6 days  

Entered as number of days since Begin

Warning Buffer

01/10/2012 -> 0 day

Entered as number of days since Financial Data

Test Upload (Dev)  01/05/2012 Performed to validate bad / missing data prior to first upload
Report Upload (Prod) 01/06/2012, 01/13/2012*First, *Second is for upload of CP applies
Report Modifications01/11/2012 - 01/12/2012If correction period (CP) applies.

9/30/2011 Period

 

Date

Note/Comment

Report Begin

09/28/2011

 

Financial Data

10/08/2011

Available date (display in emails) - FS monthend

Email Reminder

10/5/2011, 10/10/2011

7th, 12th  day from begin day

Warning Deadline

10/11/2011 -

3rd day and on from financial data

Report Cutoff

10/12/2011

Department cutoff date (display in emails)

Report 1st Upload

10/05/2011

First submission upload

Report 2nd Upload

10/14/2011

Second submission upload

Report Modifications

10/11/2011 -

 

6/30/2011 Period

 

Date

Note/Comment

Report Begin

06/21/2011

 

Financial Data

06/08/2011

Available date (display in emails)

Email Reminder

06/27/2011, 06/30/2011

2nd & 7th day from begin day

Warning Deadline

07/04/2011 - 07/10/2011

 

Report Cutoff

07/01/2011

Department cutoff date (display in emails)

Report Test Upload

07/06/2011

 

Report Upload

07/07/2011 - 07/08/2011

 

Report Modifications

07/11/2011 -

 

3/31/2011 Period

 

Date

Note/Comment

Report Begin

03/22/2011

 

Financial Data

03/08/2011

Available date (display in emails)

Email Reminder

03/24/2011, 03/29/2011

2nd & 7th day from begin day

Warning Deadline

04/01/2011 - 04/10/2011

 

Report Cutoff

04/01/2011

Department cutoff date (display in emails)

Report Test Upload

04/08/2011

 

Report Upload

04/11/2011 - 04/14/2011

 

Report Modifications

04/16/2011 -

 

12/31/2010 Period

 

Date

Note/Comment

Report Begin

12/06/2010

 

Financial Data

12/08/2010

Available date

Email Reminder

12/08/2010, 12/15/2010

2nd & 9th day from begin day

Warning Deadline

12/16/2010 - 01/10/2010

Warning starts 26 days from end of report period 01/10/2011
* earlier warning period due to Christmas break

Emails will be suspended during the break 12/21 - 1/1 resume emails after break 1/3/2010

Report Cutoff

12/20/2010

Using 12/20 for department cut off date

Report Test Upload

01/05/2011

 

Report Upload

01/06/2011 - 01/08/2011

 

Report Modifications

01/10/2011 -

 

09/30/2010 Period

 

Date

Note/Comment

Report Begin

09/10/2010

 

Financial Data

09/09/2010

Available date

Email Reminder

09/24/2010, 10/01/2010

14th & 21st day from begin day

Warning Deadline

09/30/2010 - 10/10/2010

Warning starts 10 days from end of report period 10/10/2010
(info) currently its 10 days - 09/30/2010

Report Cutoff

10/05/2010

Using 10/5 for department cut off date

Report Test Upload

10/06/2010

 

Report Upload

10/07/2010 - 10/10/2010

 

Report Modifications

10/10/2010 -

 

06/31/2010 Period

 

Date

Note/Comment

Report Begin

06/07/2010

 

Financial Data

06/08/2010

Available date

Email Reminder

06/21/2010, 06/28/2010

14th & 21st day from begin day

Warning Deadline

06/31/2010 - 07/10/2010

Warning starts 10 days from end of report period 07/10/2010
(info)
currently its 10 days - 06/31/2010

Report Cutoff

07/05/2010

Using 7/5 for department cut off date

Report Test Upload

07/06/2010

 

Report Upload

07/07/2010 - 07/09/2010

 

Report Modifications

07/10/2010 

 

  • (warning)Linking between old and new report - when report award number is changed - FederalReporting.gov is requesting us to use the 'old' award #. 
    • Since we changed to the new # from last reporting period, we had to use the linking feature to link back to the original report #
  • Several report# were also changed per agency request

03/31/2010 Period

 

Date

Note/Comment

Report Begin

03/08/2010

 

Financial Data

03/05/2010

Available date - NA for this report period

Email Reminder

03/22/2010, 03/29/2010

 

Warning Deadline

03/31/2010 - 04/10/2010

Warning starts 10 days from end of report period 04/10/2010
(info)
currently its 10 days - 03/31/2010 (probably should adjust)

Report Cutoff

04/05/2010

Using 4/5 for department cut off date

Report Test Upload

04/01/2010

 

Report Upload

04/06/2010 - 04/08/2010

 

Report Modifications

04/10/2010 -

 

12/31/2009 Period

 

Date

Note/Comment

Report Begin

12/03/2009

Release report after Office of Research ARRA training

Financial Data

12/08/2009

 

Email Reminder

12/10/2009

 

Warning Deadline

12/16/2009
- 01/10/2009

Emails will be suspended during the break 12/21 - 1/1resume emails after break 1/4/2010

Report Cutoff

12/18/2009

 

Report Reopen

01/04/2010

Reset reports to accommodate for OMB job impact calculation

Report Test Upload

01/052010

 

Report Upload

01/08/2010

Test upload failed due to CD code issues, fixed and all uploaded by 1/8/2010

Report Modifications

01/10/2010 -

 

  • (warning)Issue with Congressional District after FederalReporting site enforced the CD code rule
    • We changed all our 92697 zips to 92612 to remain in congressional district 48

09/31/2009 Period

 

Date

Note/Comment

Report Begin

09/22/2009

 

Financial Data

10/08/2009

Department entered with best available information
Accounting had reviewed data post report submission and intend to make corrects during the adjustment period

Report Cutoff

09/31/2009

Few department continued to work on reports until 10/08/2009

Report Test Upload

10/02/2009
& 10/07/2009

Did two rounds of test uploads

Report Upload

10/08/2009

Thanks to Evelyn and Bruce

Report Modifications

10/11/2009
- 10/21/2009

 

  • (warning) Agency instruct to NOT remove and reload report, but instead make modifications; this makes duplicate work for Evelyn when making any corrections
  • Award < 25K does not need to be reported; we will mark them as DEACTIVATE
  • No labels