The following is a work-in progress project plan for the UCI PMC for the 2015-2016 year

2015-2016 Objectives

    • Implement the first phase of ServiceNow’s Project app for all OIT.
    • Create a list of ServiceNow Project reports for OIT.
    • Develop \ Deploy advertisement of PM efforts within OIT.
    • ServiceNow Project Approval Framework Development (Eric T - Eric P)

Workstream Activities

  • Implement the first phase of ServiceNow’s Project app for all OIT.
    • Define requirements for phase 1 implementation.
    • Adjust access levels in ServiceNow to allow all OIT members to create, manage and close projects
    • Train managers on Project app in Service Now.
    • Define requirements for phase 2 implementation.
  • Create a list of ServiceNow Project reports for OIT.
    • Define list of projects for phase 1. 
    • Develop communication plan for report introduction to OIT
    • Create reports in Dev
    • Review reports with key PMC members for approval.
    • Move reports from Dev to Prod. 
    • Communicate report use to OIT. 
    • Define list of projects for phase 2. 
    • Develop communication plan for report introduction to OIT
    • Create reports in Dev.
    • Review reports with key PMC members for approval.
    • Move reports from Dev to Prod. 
    • Communicate report use to OIT. 
  • Develop \ Deploy advertisement of PM efforts within OIT.

General

  • PMC members work on related activities in addition to their primary work
  • Use the wiki and email for effective communication
  • Meetings for finalizing decisions needed to accomplish objectives.

Schedule/Plan

 

Workstream: Project Approval Framework

 

Item #

 

Activity

 

Assignee

Target/Actual

Start Date

Target/Actual

End Date

 

Notes

1.0Implement the first phase of ServiceNow’s Project app for all OIT.   

 

1.1Solidify list of items to include in phase 1 of implementation    
1.2Adjust access levels in ServiceNow to allow all OIT members to create, manage and close projects.     
1.3Train managers on Project app in Service Now.    
 2.0

Create a list of ServiceNow Project reports for OIT.

   
2.1Create list of required reports to generate for OIT reporting (phase 1)   
3.0Develop and execute a communications plan for OIT groups to begin using the Project application for all projects in OIT.   
3.1Create list of required documentation to illustrate the use of the Project application in ServiceNow   
4.0ServiceNow Project Approval Framework DevelopmentEric T, Eric P  