Overview

Once a project is initiated and a project manager is assigned, detailed planning, analysis and requirement definition should occur for a project.  OIT uses a comprehensive Software Development Life Cycle that ensures project implementation follows industry best practices and that projects are implemented consistently and include appropriate quality controls.  A deliverable of the planning phase will be a project plan including a task timeline, resource assignment and effort estimation. It is required that the project sponsor and any other organizations committing resources review and approve this plan. Projects proceed to the development phase after this agreement is received.

Once this detailed plan is complete, the project will be baselined for budgeted hours and timeline. This baseline information will be tracked against for project performance and will be the basis for computing project metrics.  For smaller projects, where a detailed project plan may not be required, at a minimum, the information for the budget and timeline must be completed on the Project Status Document.

Smaller projects, usually defined as those that can be implemented within a 9 month timeframe and with 2 programmer FTEs,  are usually reviewed and managed within the internal, OIT Review Committee.    Projects that are of a larger scope, more complex, or require significant budgets or FTEs, are escalated for review and monitoring by the OIT Oversight Committee.

Projects that undergo significant scope creep or requirements changes may need to re-reviewed. If there is a documented and approved change in scope or approved change in timeline, the project may be rebaselined with the approval of the OIT Oversight Committee. The OIT Oversight Committee must approve any material change in scope for an approved project. A material change in scope is defined as a 25% change in project duration or a 10% change in resource requirements.

Proposal and Project Monitoring

Approved, In Progress Projects

For projects in progress, the following will trigger a review:

  • Dollar cost exceeds 110% of baseline budget.
  • Effort in hours exceeds 110% of baseline budget
  • Project duration exceeds 125% of baseline budget
Approved, To Be Scheduled Projects
  • During the quarterly prioritization and scheduling process, any proposals that have been approved but are not scheduled to execute in the next twelve months are returned to OIT Oversight Committee for further review.
Submitted, Under Review Proposals
  • Project proposals will be accepted into the process once completed proposal information, with estimates, is received.

Projects exceeding any of the above thresholds as reported on the project status summary report, with more than 30 days left until project completion, will be reviewed by the OIT Oversight Committee at their next meeting. The OIT Oversight Committee may suspend any projects not proceeding satisfactorily at its discretion.