Summary
After receiving the completed template, requests are logged and categorized. This is sometimes followed by a technical evaluation by the OIT manager to supply additional information on the work involved.
Request Type |
Detail |
---|---|
Campus requests |
|
Internal requests |
|
Mandated requests |
|
Less than 80 hours' work or Cancelled requests |
|
Work Estimate / Technical Evaluation
- Campus requests are routed to the project manager for technical evaluation and time estimate.
- The hours estimated for the project are based on a general understanding of the project and its scope.
- Estimated hours for development projects should include all phases of the development effort including requirements gathering, design, coding and testing, documentation, and implementation. Estimates for other projects should include time for installations, coordination, tracking, and implementation.
Project Budget
- An initial budget for the project will be derived based on the project's estimated hours. This is a ballpark estimate which may be revised once the project has been scheduled and the requirements are more completely understood.
- If resources and skill leves are available to cover the budget for the project, work on the project will be scheduled accordingly.