10/1/2017 – 10/31/2017

Completed

  • Automation of the ETL process for Legacy data the ones which are complete.
  • Student Mapping Complete.
  • Additional columns added to AR Bliss Tech specifications.
  • Re-established the access to SISSHARE registrar database.
  • SZRADAP Extension script sent for review with Tom Braun.

In Progress

  • Summer Archive tables created in ODS.
  • ETL development for legacy summer tables.
  • Working with mapping of legacy registrar data into Composite table (STUDENT_COURSE) columns.
  • DCE Course Information - I&C SCI X426.53 Data Structures, Data Mining and Big Data with Python class began.

Planned

  • Continue to work with the remaining technical leads to identify the legacy data connectivity.
  • Start the ETL Development of the known Legacy inputs.

 

9/1/2017 – 09/29/2017

Completed

  • Summer ETL Access established.
  • Grad Aid Staging development put on hold as the source data development is in progress.
  • Grad Aid Change to column names completed.
  • Automation of the ETL process for Legacy data the ones which are complete.

In Progress

  • Testing of ETL connectivity for summer Database.
  • Extension on a table (SZRADAP)from Base line into ODS.
  • Student Mapping.
  • Time to degree report.

Planned

  • Continue to work with the remaining technical leads to identify the legacy data connectivity.
  • Start the ETL Development of the known Legacy inputs.

 

6/16/2017 – 08/31/2017

Completed

  • Issue on ODI Application resolved.
  • Grad Aid Staging development.
  • Grad Aid (PPS Data & Quarterly Info) composite completed.
  • Individual Access to Summer Database.
  • UG Admission Legacy data.
  • Financial Aid Legacy data.
  • Grad Division Legacy data for tables requested by Rachel.
  • Ethnicity Data.
  • KFS Data.
  • Soap UI Installed.
  • KSAMS Webservice mapping complete.
  • AR Bliss Tech specs.
  • Automation of the ETL process for Legacy data the ones which are complete.

In Progress

  • Establish the ETL connectivity for Summer database.
  • Testing for KSAMS Webservice.
  • ODI Work on Composite tables for remaining Grad Aid.
  • Extension on a table (SZRADAP)from Base line into ODS.

Planned

  • Continue to work with the remaining technical leads to identify the legacy data connectivity.
  • Start the ETL Development of the known Legacy inputs.

 

5/19/2017 – 06/15/2017

Completed

...