Mar - 31 Mar
- BI/DWH
- Develop Informatica ETL for downloading ZotMail data from UCPath
Status |
---|
colour | Yellow |
---|
title | IN PROGRESS |
---|
|
BLISS project- Reviewing the source code
- KVO
- ZotMail
- On-going support
Status |
---|
colour | Yellow |
---|
title | ON HOLDIN PROGRESS |
---|
|
UCPath - Download Employee data using ESBAT from UCPath (will resume on 06/01/2017 when UCPath has testing data)
- getIdentiyModified Download job to download getIdentity and getJobInfo from ESBAT (waiting for real data in testing env.)
- Download - completed
- Created SP for insert/update/delete to uci_employee - completed
- Test - completed
- getJobInfo
- Download - completed
- Created SP for insert/update/delete to uci_employee_appointment - completed
- Test - completed
- Developed a method to handle returned data in XML and JSON format - completed implementation. Waiting for testing data. - completed.
Status |
---|
colour | Yellow |
---|
title | IN PROGRESS |
---|
|
New lists request from Ramona Agrela - Associate Chancellor and Chief Human Resources Executive- Sub-lists of All Campus staff and Campus Supervisors by Org code
Execute Management (5000)
Academic Affairs (1000)
Student Affairs (7000)
Advancement/Development (6000)
Administrative and Business Services (3000)
Control: Accounting (9070), Finance (9060), Financial Aid and Scholarships (9040), Office of Graduate Studies (9050), and Planning (9030)
- Deployed to testing server
- eDocs
Status |
---|
colour | Green |
---|
title | COMPLETED |
---|
|
UCPath ESBAT (will resume on 06/01/2017 when UCPath has testing data)
- UCPath will have real employee data in June, 2017. Robert will re-test.
- Modified ExFiles lookup web control for using data on-demand
- Completed implementation and local testing
- Modified eDocs scanning download query
- Completed implementation and local testing
- FileNet Migration
Status |
---|
colour | Yellow |
---|
title | IN PROGRESS |
---|
|
ENTIS- imported 20 documents to FileNet Production- Migration script needs to create Tif image files and SABE server is out space.
Status |
---|
colour | Yellow |
---|
title | IN PROGRESS |
---|
|
ORTIS- Revisied migration script - Imported 2 sample documents to FileNet Dev
Status |
---|
colour | Yellow |
---|
title | IN PROGRESS |
---|
|
- UROIS - Revisied migration script- Imported sample documents to FileNet Dev
Status |
---|
colour | Green |
---|
title | COMPLETED |
---|
|
- ORTIS FileNet Import service- Created new project and implementation - completed
- Deployed to testing server - completed
- Crossed train eDocs team and eDocs will take over for production deployment.
Status |
---|
colour | Green |
---|
title | COMPLETED |
---|
|
KFS viewer - Revise viewer to handle PDF, JPEG, and TIF format- Implementation (completed)
- Deployed to edocstest server (completed)
- Testing from KFS and QA team is in progress (completed)
- Released to production on 03/19/2017 (completed)
- Issue:
- eDocs removed write permission on p8kfsviewer account. Viewer was not able to save redaction and didn't send notification to eDocs
- Fixed: send notification if viewer can't save redaction. Waiting for code review.
...