Phase | Target Date | Date Completed | Staff Assigned | |||
---|---|---|---|---|---|---|
Meeting with Facilities Management |
|
|
| |||
A. Site specifications - discussion and overview | 9 June 2010 | Sonja | ||||
1. Project includes |
|
|
| |||
CMS Test site |
|
|
| |||
A. Use Hannon Hill Cascade Server | June / July 2010 |
| ||||
May 2010 | July, 2010 | Sonja | ||||
a. Prepare Site Template |
|
|
| |||
2. Cascade Server CMS - Test Site for Facilities Management | July/ August 2010 |
|
| |||
Train FM to edit and add content | July/ August 2010 |
|
| |||
A. |
|
|
| |||
1. Make changes needed in path structure |
|
|
| |||
2. Document the changes needed for future reference. | Sept 2010 |
|
| |||
3. CSS and CMS changes needed to change style |
|
|
| |||
4. Evaluate current template for flexibility and reuse in different websites. |
|
|
| |||
Launch FM site | Fall 2010 |
| November 2010 | Sonja/Brian | ||
A. Prepare test site for launch (http://cmstest2.adcom.uci.edu) |
| 11/05/2010 | Sonja | |||
B. 1. Move resources from test to fm.uci.edu. |
| 11/16/2010 | Sonja / Brian | |||
C. Upload site |
|
|
| 11/16/2010 |
| Sonja / Brian |