4/3/2017 – 04/14/2017
Completed
- POC - Grad Division - Complete.
- Receiving the Registrar files for the legacy data input (SIF/SOC) - Complete.
- Performance Issue – Worked with Nisha to – Complete.
- Confirmation the list of source for Grad Aid - Complete.
- Development for Fund Detail Report - Complete.
- Financial Aid - Mapping spec Documentation.
In Progress
- Grad Aid - Development
- Performance issue on the ODS instance.
- Continue work with Technical leads to identify the legacy data connectivity for Informatica.
Planned
- Performance issue on the ODS instance.
- Establish the connection for the known Legacy data inputs through Informatica.
- Continue to work with the remaining technical leads to identify the legacy data connectivity.
- Start the ETL Development of the known Legacy inputs.
- Grad Div - Development
3/20/2017 – 03/31/2017
Completed
- POC - Function Rewrite - Complete.POC - Grad Division - Complete.
- Performance Issue – Worked with Nisha to identify the bottleneck – Complete.
- Grad Aid - Informatica connectivity established.
- Grad Div – Informatica connectivity established.
- Ticket created to cleanup Legacy schemas and corresponding users.
...
- Performance issue on the ODS instance.
- Continue work with Technical leads to identify the legacy data connectivity for Informatica.
- Documentation of POC Function.
Planned
- POC - Grad Division
- Establish the connection for the known Legacy data inputs through Informatica.
- Continue to work with the remaining technical leads to identify the legacy data connectivity.
- Start the ETL Development of the known Legacy inputs.
- Grad Aid - Development.
- Financial Aid - Mapping spec Documentation.
...