06-16-2015 - 06-30-2015

DWH:

In progressCompleted: JIRA#1629-Orbit to sd-orbit-db

In progressCompleted: JIRA#1636 - Prod turn over for sd-orbit-db

...

In Progress: populating uc_account_t with 2 new cols using Informatica -testing

In progress: sending missing FS dept codes to Accounting

Completed: Darla request list

Completed: Incident#0030279-adding FS dept code for PCS

In Progress: PCS could not be created for fund: 78701

In Progress: Incident#0029563- Adding testid's for Facility from test0401-0430 - reply to Tom to used other userid

vacation: 06/22-06/28

DWH-PPS:

...

In progress: create summary of ldap_people table in sd-lunar.dss_kfs

PPS:

In progress: Incident#0029163-UCOP PPS screen error - add David to ticket

UCPath:

Kuali:

Training:

 Continue: Informatica part 2

...