6/15/2015 - 6/26/2015

Completed

  • Sandbox access to KC application.
  • Initial ODS table build in in our dev DB environment.
  • ETL design to populate initial ODS.
  • Initial SPA annual Report presentation for the Office of Research staff.
  • KC proposal ODS data and sample report demo.
  • Informatica Analyst connection error resolved.
  • Created a sample data profile on KC table.

In Progress

  • Profiling KC database schema and data.
  • Testing Informatica Analyst feature set and functionality.
  • Aiding with troubleshooting/testing of Talend/Informatica conversion.

Planned

  • Continue to profile KC database schema and data.
  • Additional annual reports requested by Office of Research staff.

 

6/1/2015 - 6/12/2015

Completed

...