Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

12/3013/2017 - 2/1024/2017

Completed

  • New awards by purpose Cognos report complete.
  • Code review for all PURAP TEM objects for production deployment.
  • UCLA Informatica object import for UCPath. Shared Additional fact table for KC Negotiation star completed.
    • Informatica workflow updated.
    • Cognos framework package updated with new star schema grouping updated.
  • OR data warehouse related tables migrated to Solar for OIR to access.
  • Common award dimension feasibility analysis. 
    • SPA/KFS GAP analysis.
    • Accounting will have Janine create a separate award dimension.
    • Will revisit at a later date.
  • Aiding the Middleware team in configuring/troubleshooting Informatica LDAP loading workflows.
    • Connectivity issue to ldap-dev resolved.  Issue related to TLS setting in addition to port setting on the Informatica connection object.
  • JIRA's completed
    • Jira Legacy
      serverOIT JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId252346bd-c418-34af-94a0-0709b2108812
      keyKFSDW-1611
  • Service-now incidents completed:

In Progress

  • SPA awards dimensional model design
    • Dimensional modeling
    • Informatica mapping design
    • Cognos Framework model design.
  • Informatica session statistics auditing capability survey for COMPASS workflows.
    • Designing POCs for several different design approaches. 
  • KC proposal dimension daily loading mapping design.
  • Clinical trials Cognos report for OR (On hold) 
    • Need additional fields in the proposal ODS table.
    • ETL and Cognos framework package needs to be adjusted.
  • New OR dev and prod database migration.
    • All Informatica/Cognos connections need to be changed.
    • Firewall rules for production.
    • Connectivity testing for production. 
  • Zena Agent install on etl-dev.
    • Waiting on firewall exceptions to be completed by the security team.

Planned

  • Informatica SRAQ.


1/30/2017 - 2/10/2017

Completed

  • New awards by purpose Cognos report complete.
  • Code review for all PURAP TEM objects for production deployment.
  • UCLA Informatica object import for UCPath. 
    • Shared folders created for all source, target, and transformations. 
  • Informatica developer training prep work complete.
    • Confirmed for 3/6-3/9 @AIRB1020
  • Presentation slides prep work for OIR DW information session.
  • JIRA's completed
    • Jira Legacy
      serverOIT JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId252346bd-c418-34af-94a0-0709b2108812
      keyKFSDW-1596
  • Service-now incidents completed:

In Progress

  • Additional fact table creation for KC Negotiation star.
  • Aiding the Middleware team in configuring/troubleshooting Informatica LDAP loading workflows.
    • Also migrating/testing connectivity to new ldap-dev server.
  • Clinical trials Cognos report for OR (On hold) 
    • Need additional fields in the proposal ODS table.
    • ETL and Cognos framework package needs to be adjusted.
  • New OR dev and prod database migration.
    • All Informatica/Cognos connections need to be changed.
    • Firewall rules for production.
    • Connectivity testing for production. 
  • Zena Agent install on etl-dev.
    • Waiting on firewall exceptions to be completed by the security team.

...

  • UCLC Training
    • Sexual Harassment Prevention
    • Cyber Security Awareness
  • Awards by purpose Cognos report for 2015-2017 fiscal years
  • Awards by sponsor by school Cognos report for Q1 2017.
  • Code Review for OIR Compass ETL.
  • Daily GL dev nightly loading changed back to KFSDAY2.
  • ETL data flow overview meeting for OIR reporting team.
  • SISDEV connectivity from Informatica.
    • stunnel setup complete.
    • ODBC source setup and testing complete on etl-dev.
  • JIRA's completed
    • Jira Legacy
      serverOIT JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId252346bd-c418-34af-94a0-0709b2108812
      keyKFSDW-1573
    • Jira Legacy
      serverOIT JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId252346bd-c418-34af-94a0-0709b2108812
      keyKFSDW-1579
    • Jira Legacy
      serverOIT JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId252346bd-c418-34af-94a0-0709b2108812
      keyKFSDW-1580
    • Jira Legacy
      serverOIT JIRA
      columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
      serverId252346bd-c418-34af-94a0-0709b2108812
      keyKFSDW-1587
  • Service-now incidents completed:

In Progress

  • UCLA Informatica object import UCPath.
    • Need to create shared folders. 
  • Informatica developer training proposal prep work.
    • AIRB training room requested for (3/6-3/9)
    • Received adjusted price quote for Level 1 Developer course.
    • Received customization confirmation from Informatica University.
  • Clinical trials Cognos report for OR (On hold) 
    • Need additional fields in the proposal ODS table.
    • ETL and Cognos framework package needs to be adjusted.
  • New OR dev and prod database migration.
    • All Informatica/Cognos connections need to be changed.
    • Firewall rules for production.
    • Connectivity testing for production. 
  • TEM data mart development code review and deployment prep work.
  • Zena Agent install on etl-dev.
    • Waiting on firewall exceptions to be completed by the security team.

...