Attending: Kian Colestock, Diane Dunn, Ying Kussman, Jeff Martin, Steve Noh, Eric Puchalski, Paul Sheirich, Eric Taggart, Briandy Walden
Absent: Steve, Paul
Location: 232 MSTB
ReadyTalk: www.readytalk.com 1-866-740-1260 Conference Code: 8240536
Agenda/Notes:
- Project Approval Framework Workstream
- ServiceNow Implementation Update
- Initial OIT launch in late November - primary focus on incident management for many OIT groups
- https://ucidev.service-now.com/
- May need to contact EricP for some permissions re: PM capabilities (EricP will setup for this group)
- EricP/Kian looking at PM and portfolio aspects
- Comparing SmartSheet and SN
- Kian to provide preview of PM aspects at next meeting?
- What other types of projects could follow this framework (besides in-house or vendor software projects)?
- Information Security
- WHC Information Security Risk Remediation (Jeff)
- Unit Security Plan Development (like the past GD and OR security plan projects that are already completed)
- NetOps Engineering
- VoiceMail Upgrade (Diane)
- Client Request Project: NetOps Wireless Expansion in Animal Housing Areas
- Infrastructure
- OITDC Secondary Site
- ...
- Information Security
- OIT Project Life Cycle Approvals
- Draft Approval Framework
- Adapting the Project Approval Framework to existing OIT Procedures
- EricP updated OIT SDLC chart with these 3 review/approval gates
- Discussion re: Projects already underway
- Some benefits to backfilling w/ proposal and affirming prior approvals
- We can still work an in-progress or previously approved project with this approval framework
- SLAs and OLAs can help to get off-track projects back closer to on-track
- What should be required for each phase?
- Initiation:
- OIT Project Proposal
- Implementation:
- Functional requirements, technical/design/solution specs, project plan with schedule. resource requirements (especially if cross-team involvement is required)
- Other groups that may be asked to review the implementation plans:
- Security, Architecture Review Board, ...
- Go-Live:
- Confirmation that products/services to be delivered meet expected requirements/plans/processes
- Official customer acceptance and production readiness sign-off
- Artifacts to demonstrate proper documentation was completed, required processes were followed, all tasks/issues are adequately closed
- Go-live plan, post-production support plan, closeout activities
- Initiation:
- What groups could conduct reviews/approvals for each phase?
- Software projects: OIT Software Development Directors Group
- PM for a given project should be able to define who needs to be in the respective review/approval group for each phase
- Have the OIT Director above the PM for the project be the main approval point
- Consider use of the OIT Architecture Review Board
- Consider FYIs to other OIT DIrectors
- ...
- /wiki/spaces/public/pages/31361236
- Current projects to test workflow?
- Eric T has a few at different stages:
- Ready for Initiation: Tick@Lab Implementation - Animal Research Administration System replacement project
- Ready for Implementation: (maybe) Streamlining IRB Unanticipated Problem Reporting
- Ready for Go Live: (almost) KC 5 Upgrade
- Any others?
- Eric T has a few at different stages:
- ServiceNow Implementation Update
- Tools and Resources Workstream
- Eric P distributed a range of existing materials related to PMLC and SDLC
- Much of these resources are already organized /wiki/spaces/public/pages/31361236
- Review results of Eric P's PM survey for best practices and tools we might recommend
- Summarize existing tools on resource wiki page
- Terminology matters
- Discussion: Why so many tools and/or pain points and/or better practices
- Eric P distributed a range of existing materials related to PMLC and SDLC
- Consultative Project Support Workstream
- Discussion: What types of support do we think we could provide that would be helpful?
- UCPath and SIS may require local PM support/tools - perhaps we can talk about those gaps and how they might be addressed via this group
- Any others?
- Discussion: What types of support do we think we could provide that would be helpful?
- Other
- ...
- Next Meeting
- Friday November 21 1:00pm MSTB 232
- ...
Action Items:
- Jeff and Diane work through Project Approval Framework documentation recommendations (project proposal, etc.) for their respective projects (WHS Security, Voicemail)
- Jeff will share his notes - won't be at next meeting
- Schedule ServiceNow discussions with ...
- Create an Exchange email distribution list for the PMC group oit-pmc@uci.edu
- Task some with follow-ups per above
- Jeff/Eric T will setup another interim meeting
Future Agenda Items:
- Discuss how the OIT Project Proposal and other review/approval artifacts work for non-software projects
- Informal ServiceNow PM demo
- Aligning language and steps in the OIT Unified SDLC and the Project Approval Framework
- ...
Parking Lot Topics:
- ...