The following is a work-in progress project plan for the UCI PMC for the 2015-2016 year

2015-2016 Objectives

Workstream Activities

General

Schedule/Plan

 

Workstream: Project Approval Framework

 

Item #

 

Activity

 

Assignee

Target/Actual

Start Date

Target/Actual

End Date

 

Notes

1.0Implement the first phase of ServiceNow’s Project app for all OIT.   

 

1.1Solidify list of items to include in phase 1 of implementation    
1.2Adjust access levels in ServiceNow to allow all OIT members to create, manage and close projects.     
1.3Train managers on Project app in Service Now.    
 2.0

Create a list of ServiceNow Project reports for OIT.

   
2.1Create list of required reports to generate for OIT reporting (phase 1)   
3.0Develop and execute a communications plan for OIT groups to begin using the Project application for all projects in OIT.   
3.1Create list of required documentation to illustrate the use of the Project application in ServiceNow