Overview
OIT senior management, directors, managers and stakeholders in supported business units seek current and complete information on active projects for a broad range of reasons. As OIT's primary ITSM platform, we should be able to leverage ServiceNow for more complete and consistent project tracking and reporting across the entire organization.
Objectives
Enable OIT staff and managers to record newly proposed and existing projects within ServiceNow
Keep the OIT Project Request Log current
Support the review and approval of project requests by OIT divisional Directors
Provide status reports with project health indicators and textual information on all active OIT projects - using information entered/updated by the OIT staff who are executing/managing the projects
That can also be delivered as PDF documents to stakeholder unit management
Organize projects and status reports with portfolios that represent OIT Divisions, OIT Teams, campus stakeholder units, etc
Process
Create a new SN Project record using the SN Project Intake Form (via the Service Catalog)
Or directly via the SN Project application
Add relevant information to the SN Project record such as the Project Manager, technical team, assignment group, etc.
The minimum SN Project record data elements include:
...
Create a new SN Portfolio Project record to connect the new SN Project with at least one existing SN Portfolio
Add that Portfolio Project to other SN Portfolios as needed (not yet sure how to do this in SN)
Create additional Portfolio records as needed to organize work into useful groupings
Update the SN Portfolio Project record monthly to communicate project status/risks/etc
The minimum SN Portfolio Project record data elements include:
...
Optionally use SN Project Tasks and related features to manage the implementation/execution of the project
Managers may elect to use other project management tools instead - such as JIRA, SmartSheet, MS Project, etc.
Other Required Changes
The OIT Project Request Log can be kept on the wiki and manually updated by someone (maybe the new OIT PM) as newly proposed SN Projects are defined
OIT Directors can optionally review/approve newly proposed projects following any process they prefer without using any SN workflow features
Roles/Responsibilities
Project Manager
Responsibility for the 4 (or 5) process steps above
Could delegate some of the items to the technical leads
Technical Lead
Conduct projects (track via SN Project record if the PM requests it)
Provide status updates to the PM
OIT Divisional Directors
Review Portfolio Project Status Reports
Monitor/review incoming projects as required
Help ensure their divisional managers are referencing/maintaining all active/pending projects in SN
OIT PM (PMO)
Manage the OIT Project Request Log
Help ensure all OIT managers are representing projects in SN
Provide reports to OIT Divisional Directors
Stakeholders
Receive/review PDF Portfolio Project status reports
Next Steps
Eric T to finish drafting his ideas for the minimum steps and SN Portfolio/PortfolioProject/Project data elements to be maintained on all active projects for reporting purposes
Eric P to document the minimum steps and SN Portfolio/PortfolioProject/Project data elements to be maintained on all active projects for reporting purposes
Develop a proposal for OIT PMC Review/Discussion/Approval
Review with the PMC
Jeff Martin asked for this work to be completed by the end of August