Feeder Systems:
Task Name | % Complete | Last Update |
HR QuickTemp (Feeder) | 100% | |
OIT - Telecommunication (Feeder) | 100% | |
Bookstore Recharges (Book, TOES) (Feeder) | 100% | |
EH&S (Feeder) | 100% | |
AFS - C&G Billing (Feeder) | 100% | |
Payroll (Feeder) | 100% | |
Campus Billing System Online (Feeder)99% | 60% | 07/02/2013 |
OPAL Cashiering and Campus Online Deposit (Feeder) | 99%60% | 07/02/2013 |
Foxpro/ARC (Feeder)99% | 60% | 07/02/2013 |
Student Housing (Feeder) | 98% | |
Campus Credit Card System (Feeder)97% | 60% | 07/02/2013 |
Facilities (Feeder) | 92% | |
UNEX applications (Feeder) | 85% | |
PI Report (Feeder) | 70% | |
Library (Feeder) | 65% | |
Student Billing System (Feeder)56% | 60% | 07/02/2013 |
Biological Sciences (Feeder) | 50% | |
Physical Sciences (Feeder) | 50% | |
UPS (University Physicians & Surgeons) (Feeder) | 50% | |
Student Loan and Collections Re-write (Feeder)36% | 30% | 07/02/2013 |
Parking & Transportation - TDS Systems (Feeder) | 53% | |
UCIMC (Feeder) | 40% | |
Cost Sharing System (Feeder) | 10% | |
Office of Research (Feeder) | 9% | |
Graduate Division (Feeder) | 8% |
Shadow Systems:
Task Name | % Complete | Last Update | |
Pharm Sci Tracking System | 100% | ||
eDocs: Rapid Return | 75% | 06/20/2013 | |
OIT - Data Warehouse (Cognos) - Val will link main project plan | 53% | ||
HR - Equity Advisor | 12% | ||
HR - FastClass | 12% | ||
HR - QuickRec/Greentree | 12% | Tax Relief Act (TRA) system | 0% |
DEFT (Employee might convert to ucop, but Students will not) | 10% | 07/02/2013 | |
Tax Relief Act (TRA) 0%system | 5% | 07/02/2013 | |
HR - ContractPro | 0% | ||
AFS - Payroll Certification0% | 15% | 07/05/2013 | |
Gift Form0% | 30% | 07/05/2013 | |
OIT - Mobius Reports | 0% | ||
SNAP | 0% | ||
Student Affairs TimeKeeper | 0% | ||
eDocs: Shredding, Scanning and Misc. (Provide a total recharge amt and enter directly into KFS) | 0% | ||
SRDV (Online Reports - SM) | 0% | ||
Learning and Academic Resource Center to SBS Feeds | 0% | ||
SOM Decision Support | 0% | UCIMC Facilities | 0%
Detailed Project Plan With Completion Percentage:
...