Email Notification Schedule

...

(star) Currently the emails notificaiton is hold off for this report period until confirmed with Evelyn for the schedule

Reporting period of 12/31/2009

Email Type

When to send emal

Example Time

Event Note

Recipients

 

Scheduled Emails

 

 

 

new_award

New Award created
(green star)
arbitrary date

8 12/0103/2009

New ARRA Award, users have access to report

Department, PI
 

report_reminder

One month prior to last day of Reporting
2 weeks prior
1 week prioir

8/30/2009,
9/16/2009,
9/23/2009 days after report period being
(can be schedule to send more frequently)

12/10/2009...
more

Email to Department and PI that information must be completed by last day of reporting period (9/30/2009)

Department, PI
 

warning_email

Last day of reporting for 10 days (end of report period)

9/30 x days after the financial data date until all reports submmited

12/18/2009 - 1001/10/2009 2010
(optional turn off during the break)

WARNING Email - Department and PI must have completed their sections

Department, PI, C&G

 

Per-Request Emails

 

 

 

report_revise

Report is revised by Administrator

when report is revised

Administrator rejected report and request Department to make modification

Department, PI
 

report_reset

Report status is reset by Administrator

when report status is reset

Administrator reset status of report for Department to make modification

Department, PI

 

sent_federal
(warning)
disabled

Report marked as uploaded
10/5/2009 - 10/10/2009

when report is marked as uploaded

Administrator mark report as uploaded
(warning)
currently disabled as reports seem to be updated and re-upload more often than expected

Department, PI

 

 

 

 

 

 

 

Administration

...

Emails

Email Type

When to send emal

Example Time

Event Note

Recipients

new admin_award

New Award created

8/01/2009

New ARRA Award, users have access to report

Department, PI

 

report_reminder

One month prior to last day of Reporting
2 weeks prior
1 week prioir

8/30/2009,
9/16/2009,
9/23/2009

Email to Department and PI that information must be completed by last day of reporting period (9/30/2009)

Department, PI

 

warning_email

Last day of reporting for 10 days (end of report period)

9/30/2009 - 10/10/2009

WARNING Email - Department and PI must have completed their sections

Department, PI, C&G

 

report_revise

Report is revised by Administrator

when report is revised

Administrator rejected report and request Department to make modification

Department, PI

 

report_reset

Report status is reset by Administrator

when report status is reset

Administrator reset status of report for Department to make modification

Department, PI

 

sent_federal

Report marked as uploaded

10/5/2009 - 10/10/2009

Administrator mark report as uploaded

Department, PI

 

 

 

 

 

 

 summary

25 days from end of reporting (1/10/2010)
until last

12/18/2009 - 01/10/2010
(optional turn off during the break)

Summary email of all report not yet submitted