Phase | Target Date | Date Completed | Staff Assigned |
---|---|---|---|
Meeting with Kathy Haq/ A&BS |
|
|
|
A. Site specifications - discussion and overview |
| 6 August 2012 | Sonja |
1. Project includes |
|
|
|
B. Prepare Project Proposal a. Submit to Ying for review b. Send to Kathy for edits c. Receive Project Proposal final | August 2012 13 Aug 2012 5 Sept 2012 | 10 August 2012 5 Sept 2012 5 Sept 2012 | Sonja Ying Sonja from Kathy H. |
Site Preparation | |||
| 6 August 2012 | 7 Aug 2012 | Todd McGill |
2. Site name - Request DNS for www.ucpath.uci.edu and ucpath.uci.edu | 6 Aug 2012 | 9 Aug 2012 | Brian Craft |
3. Test site - Request and register cmstest4.oit.uci.edu with a CNAME of 'abs.oit.uci.edu' | 7 Aug 2012 | 31 Aug 2012 | Brian Craft |