- Overview
- OIT senior management, directors, managers and stakeholders in supported business units seek current and complete information on active projects for a broad range of reasons. As OIT's primary ITSM platform, we should be able to leverage ServiceNow for more complete and consistent project tracking and reporting across the entire organization.
- Objectives
- Enable OIT staff and managers to record newly proposed and existing projects within ServiceNow
- Keep the OIT Project Request Log current
- Support the review and approval of project requests by OIT divisional Directors
- Provide status reports with project health indicators and textual information on all active OIT projects - using information entered/updated by the OIT staff who are executing/managing the projects
- That can also be delivered as PDF documents to stakeholder unit management
- Organize projects and status reports with portfolios that represent OIT Divisions, OIT Teams, campus stakeholder units, etc
- Process
- Create a new SN Project record using the SN Project Intake Form (via the Service Catalog)
- Or directly via the SN Project application
- Note: It looks like a Portfolio Project record with the same Project Name/Short Description is also created automatically
- So step 3 below may be able to be streamlined
- Add relevant information to the SN Project record such as the Project Manager, technical team, assignment group, etc.
- The minimum SN Project record data elements to include are referenced at the lower section of this page
- Create a new SN Portfolio Project record to connect the new SN Portfolio Project with at least one existing SN Portfolio
- How To: Start from an existing Portfolio for the project to be associated under, select the New button from the "Project View" tab, enter the related info, including a reference to the SN Project record
- The minimum SN Portfolio Project record data elements to include are referenced at the lower section of this page
- Add that Portfolio Project to other SN Portfolios as needed
- Portfolio Projects should be associated with Portfolios for:
- The related OIT Stakeholder Business Unit
- The related OIT Division
- The related OIT Team
- The "OIT Comprehensive Portfolio"
- How To: Start from the Portfolio Project record, select the Edit button from the "Portfolio" tab, add the related Portfolio(s) and save.
- OR: Start from a Portfolio record, select the Edit button from the "Project View" tab, add the related Portfolio Projects and save
- Create additional Portfolio records as needed to organize work into useful groupings
- How To: Start from an existing Portfolio for the project to be associated under, select the New button from the "Project View" tab, enter the related info, including a reference to the SN Project record
- Update the SN Portfolio Project record monthly to communicate project status/risks/etc
- The minimum SN Portfolio Project record data elements to include are referenced at the lower section of this page
- Focus on providing brief updates to the "Risk", "Risk Comment", "% Complete" and "% Complete Comment" items as they are the key indicators for most status reports
- Also update planned and actual start/end dates as needed
- Optionally use SN Project Tasks and related features to manage the implementation/execution of the project
- Managers may elect to use other project management tools instead - such as JIRA, SmartSheet, MS Project, etc.
- Create a new SN Project record using the SN Project Intake Form (via the Service Catalog)
- Other Required Changes
- The OIT Project Request Log can be kept on the wiki and manually updated by someone (maybe the new OIT PM) as newly proposed SN Projects are defined
- OIT Directors can optionally review/approve newly proposed projects following any process they prefer without using any SN workflow features
- Roles/Responsibilities
- Project Manager
- Responsibility for the 4 (or 5) process steps above
- Could delegate some of the items to the technical leads
- Technical Lead
- Conduct projects (track via SN Project record if the PM requests it)
- Provide status updates to the PM
- OIT Divisional Directors
- Review Portfolio Project Status Reports
- Monitor/review incoming projects as required
- Help ensure their divisional managers are referencing/maintaining all active/pending projects in SN
- OIT PM (PMO)
- Manage the OIT Project Request Log
- Help ensure all OIT managers are representing projects in SN
- Provide reports to OIT Divisional Directors
- Stakeholders
- Receive/review PDF Portfolio Project status reports
- Project Manager
- Next Steps
- Eric T to finish drafting his ideas for the minimum steps and SN Portfolio/PortfolioProject/Project data elements to be maintained on all active projects for reporting purposes
- Eric P to document the minimum steps and SN Portfolio/PortfolioProject/Project data elements to be maintained on all active projects for reporting purposes
- Develop a proposal for OIT PMC Review/Discussion/Approval
- Review with the PMC
- Jeff Martin asked for this work to be completed by the end of August
...