  • Overview
    • OIT senior management, directors, managers and stakeholders in supported business units seek current and complete information on active projects for a broad range of reasons.  As OIT's primary ITSM platform, we should be able to leverage ServiceNow for more complete and consistent project tracking and reporting across the entire organization.
  • Objectives
    • Enable OIT staff and managers to record newly proposed and existing projects within ServiceNow
    • Keep the OIT Project Request Log current
    • Support the review and approval of project requests by OIT divisional Directors
    • Provide status reports with project health indicators and textual information on all active OIT projects - using information entered/updated by the OIT staff who are executing/managing the projects
      • That can also be delivered as PDF documents to stakeholder unit management
    • Organize projects and status reports with portfolios that represent OIT Divisions, OIT Teams, campus stakeholder units, etc
  • Process
    1. Create a new SN Project record using the SN Project Intake Form (via the Service Catalog)
      1. Or directly via the SN Project application
    2. Add relevant information to the SN Project record such as the Project Manager, technical team, assignment group, etc.
      1. The minimum SN Project record data elements include:
        • ...
    3. Create a new SN Portfolio Project record to connect the new SN Project with at least one existing SN Portfolio
      1. How To: Start from an existing Portfolio for the project to be associated under, select the New button from the "Project View" tab, enter the related info, including a reference to the SN Project record
      2. Add that Portfolio Project to other SN Portfolios as needed (not yet sure how to do this in SN)
        1. How To: Start from the Portfolio Project record
      3. Create additional Portfolio records as needed to organize work into useful groupings
    4. Update the SN Portfolio Project record monthly to communicate project status/risks/etc
      1. The minimum SN Portfolio Project record data elements include:
        • ...
    5. Optionally use SN Project Tasks and related features to manage the implementation/execution of the project
      1. Managers may elect to use other project management tools instead - such as JIRA, SmartSheet, MS Project, etc.
  • Other Required Changes
    • The OIT Project Request Log can be kept on the wiki and manually updated by someone (maybe the new OIT PM) as newly proposed SN Projects are defined
    • OIT Directors can optionally review/approve newly proposed projects following any process they prefer without using any SN workflow features
  • Roles/Responsibilities
    • Project Manager
      • Responsibility for the 4 (or 5) process steps above
      • Could delegate some of the items to the technical leads
    • Technical Lead
      • Conduct projects (track via SN Project record if the PM requests it)
      • Provide status updates to the PM
    • OIT Divisional Directors
      • Review Portfolio Project Status Reports
      • Monitor/review incoming projects as required
      • Help ensure their divisional managers are referencing/maintaining all active/pending projects in SN
    • OIT PM (PMO)
      • Manage the OIT Project Request Log
      • Help ensure all OIT managers are representing projects in SN
      • Provide reports to OIT Divisional Directors
    • Stakeholders
      • Receive/review PDF Portfolio Project status reports
  • Next Steps
    • Eric T to finish drafting his ideas for the minimum steps and SN Portfolio/PortfolioProject/Project data elements to be maintained on all active projects for reporting purposes
    • Eric P to document the minimum steps and SN Portfolio/PortfolioProject/Project data elements to be maintained on all active projects for reporting purposes
      • Develop a proposal for OIT PMC Review/Discussion/Approval
    • Review with the PMC
    • Jeff Martin asked for this work to be completed by the end of August