12/05/2016

Attendees:  Eufemia, Matt, Ursula, Pramod, Tammy

Issues and bugs:

Pramod to start work on KFSDW-1545.

Tasks:

Ursula:  Continue working on KFSDW-1507.  READY for TEST, KFSDW-1429, KFSDW-1384. Continue to work on expediting JIRAs (KFSDW-1546) Has question for Susan. Continue to work on building PURAPP packages (PO_ITEM & PO_ITEM_ACCTG).

Eufemia:  Continue working with Maria on KBM reports ,

Jira Legacy
serverOIT JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId252346bd-c418-34af-94a0-0709b2108812
keyKFSDW-1517
Jira Legacy
serverOIT JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId252346bd-c418-34af-94a0-0709b2108812
keyKFSDW-1519
, are READY FOR TEST.  
Jira Legacy
serverOIT JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId252346bd-c418-34af-94a0-0709b2108812
keyKFSDW-1518
,
Jira Legacy
serverOIT JIRA
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId252346bd-c418-34af-94a0-0709b2108812
keyKFSDW-1503
KFSDW-1540 continue working on.  Waiting to hear back on KFSDW-914 from Kevin (and whether KFSDW-1323 is needed still).

Matt: Currently working on KFSDW-906.

Tammy: Tammy waiting for more updated spec on KFSDW-944.

Anh:  Analytics ETL undergoing UAT.  Working on KFS related tasks. Currently working on KFSDW-1496.

Pramod:  Working on KFS Upgrade activities. 

11/28/2016

Attendees:  Eufemia, Matt, Ursula, Anh

...

Pramod - Working on new addition to balance table, modification of ETL for ITD balances. Design for AP data mart.

 

 

5/2/2016

Bug Review

 KFSDW-1115 - Eufemia talked to Mat Wilson about FP4, they are trying to include it with security updates in Cognos. The BI team is still evaluating how to test the update.

KFSDW-1244 - Waiting for Accounting to test

All others are ready to deploy or on hold

 

Issues

KFSDW-1195 - Doc details action taken code - fix is in DB but Matt doesn't see it fixed on the FM package on dev. Matt will try to test this in the framework project directly instead of in the report.

KFSDW-974 - Report devs still need to test ODS tables. We have about 157 reports that will need to be tested. Eufemia will create a JIRA for testing.

KFSDW-1007 - Specs need to be updated. Valerie will discuss in our meeting with Accounting.

...

Eufemia - Waiting for response from Diane on KFSDW-979. Waiting for Kitty on KFSDW-345

...