6/13/2016

Bug Review

KFSDW-1314 is still waiting for test

Issues

Talend ODS job needs to be rerun today due to Oracle server move (affect Account Transactions and PDP Check reports).

Pramod and Eufemia will be working on speeding up the RAFG Detail report.

Need to reconfig connection Oracle database due to server move (change config files).

Tasks

Matt - working on documentation for KFS reports.  Any changes or fixes for reports "Ready For Test" will be worked on with Ursula.  Working on how to join the PO View to GL Entries.

Anh - Talend ODS jobs to have new connection for the Oracle Server move.  Changing KFS database passwords for annual password change (incl. Secret Server). 

Tammy - working on non KFS, LDAP people jobs, etc.

Eufemia - documenting KFS Report Development Workflow, getting RAFG report ready for test (working on performance), finish testing for ODS tables.

Ursula - Training with Matt on KFS reports (ready for test), meeting with Melissa regarding AR Report.

Pramod - deploying KFSDW-1289 on Friday, possible deploy KFS_D_RAFG as well (datatype for dimension), working with Analytics for PURAPP model.

6/6/2016

Bug Review

KFSDW-1313 was put on hold by Accounting. We will work on it after fiscal year end.

...

Pramod - Working on new addition to balance table, modification of ETL for ITD balances. Design for AP data mart.

 

 

5/2/2016

Bug Review

 KFSDW-1115 - Eufemia talked to Mat Wilson about FP4, they are trying to include it with security updates in Cognos. The BI team is still evaluating how to test the update.

KFSDW-1244 - Waiting for Accounting to test

All others are ready to deploy or on hold

 

Issues

KFSDW-1195 - Doc details action taken code - fix is in DB but Matt doesn't see it fixed on the FM package on dev. Matt will try to test this in the framework project directly instead of in the report.

KFSDW-974 - Report devs still need to test ODS tables. We have about 157 reports that will need to be tested. Eufemia will create a JIRA for testing.

KFSDW-1007 - Specs need to be updated. Valerie will discuss in our meeting with Accounting.

...

Eufemia - Waiting for response from Diane on KFSDW-979. Waiting for Kitty on KFSDW-345

...